Quail Creek- update
The high pressure cleaning started today. Today we have completed buildings: 3, 4, 2, 6, 5.
Tuesday we are going to do buildings: 19, 18, 17, 14, 13
Wednesday we will be finishing the remaining buildings.
**Weather permitting.
Then we will be working onĀ garages and the pool area until after the holidays. We are requesting that all decorations be down by January 4th- when the painting of the units will be starting.
For questions, concerns or comments, please email us here
or call us at 909-980-4059.